Have you sat at the red light on U.S. 2/7 at South Park Drive, watched the interchange ahead look half empty, and wondered why you're still waiting? The light isn't broken. Since early Thursday, September 17, 2026, when Vermont's first diverging diamond interchange went live at I-89 Exit 16, those holds have been part of the design.
The Exit 16 you'll drive this winter is also a temporary version. The traffic pattern is finished. The signal timing, some of the pedestrian signals and the shared-use path aren't. Once you know which parts are permanent, the strange moments on your Costco run start to make sense.
According to the VTrans project page, drivers can expect longer holds on U.S. 2/7 northbound at South Park Drive and southbound at Mountain View Drive than they had before the interchange opened. Those holds are intentional. They control how much traffic enters the interchange and balance demand from every direction, and VTrans says the goal is to manage the whole Exit 16 area rather than favor one road or one movement.
So the system works like a funnel. It holds traffic at the two outer intersections so the crossovers in the middle don't back up. On opening morning, a VTrans official explained the reasoning to WCAX: "The more traffic we can keep free-flowing, the safer, in theory, the whole interchange will be."
The drivers WCAX interviewed that morning were mostly relaxed about it. "It was a little intimidating at first, but I think it's going to work out well," said Tammy of Sheldon. "Traffic seems to be moving a little smoother." Tractor-trailer driver Jordan Brace of Williston said the turn was "a little tight coming around," but he made it easily.
That's a lot of process for one mile of road. VTrans is rebuilding about a mile of U.S. 2/7, from the Colchester-Winooski town line to just past Sunderland Woods Road. WCAX reported that the interchange opened after 14 years of planning and more than three years of construction. The work has two contracts, both held by S.D. Ireland Brothers Corporation:
| Phase | Timing | Work | Approximate cost |
|---|---|---|---|
| Phase 1 | 2023 | Utility relocations, ledge removal, retaining walls for future bike and pedestrian routes, drainage | $7.5 million |
| Phase 2 | Summer 2025 to summer 2027 | The DDI itself, added turn lanes, bike and pedestrian facilities | $22.5 million |
The DDI is easier to drive than to describe. VTrans breaks it into six steps:
Step six is the one that changes your routine the most. Coming off the interstate, a left turn now means yielding to traffic from only one direction. VTrans also notes that U-turns back onto I-89 are easy, which helps if you miss your exit. Left turns onto the on-ramps happen without crossing oncoming traffic, which is why the whole thing is built this way.
If you'd like to see it before you drive it, VTrans has driving animations for four trips: Winooski toward Colchester, Colchester toward Winooski, and both I-89 exits onto U.S. 2/7. VTrans also brought a driving simulator to the Champlain Valley Fair before the opening so people could try the left-side crossover in advance, WCAX reported.
The raised concrete islands crews built in the weeks after opening do a job too. VTrans says the raised channelizing islands are meant to cut down on wrong-way highway entries.
The north end of the corridor is where the temporary setup shows most. The Costco warehouse at 218 Lower Mountain View Drive is there, with its gas station, pharmacy, tire center and food court. Shaw's is on Mountain View Drive.
On October 23, VTrans took down the old span-wire signals at U.S. 2/7 and Mountain View Drive/Lower Mountain View Drive and switched on new mast-arm signals. The intersection still runs on temporary timing and phasing. For now, drivers turning left out of Lower Mountain View Drive get only a short protected left-turn phase.
Some of the new signal heads and pedestrian indicators will stay dark until next construction season. That's when crews install new controller cabinets and finish the final paving and pavement markings. After that, VTrans plans to give Mountain View Drive and Lower Mountain View Drive separate signal phases, which it says will improve traffic flow there.
So if the left turn out of the Costco side feels shorter than you'd like this winter, you're seeing the interim setup. The finished signal timing at that intersection doesn't arrive until next construction season.
The biggest change for anyone who isn't driving isn't finished yet. VTrans plans shared-use paths along both sides of U.S. 2/7 through the interchange, with ramps just north and south of it. Sidewalks will extend south to South Park Drive and north to Mountain View Drive, and marked shoulders will continue to Sunderland Woods Road.
In its October 30 update, VTrans said crews were still pouring concrete for that path through the interchange, along with the pad for a new bus shelter on Mountain View Drive.
That bus shelter connects to a recent transit change. Green Mountain Transit rerouted Route #9 Winooski starting Monday, August 24, 2026, to serve Shaw's on Mountain View Drive. GMT said the change would improve grocery access and service to Water Tower Hill. A grocery-store bus stop with a shelter beside a new path along a rebuilt corridor makes Exit 16 more usable for people who aren't driving.
Here's what's left on the VTrans calendar:
| When | What VTrans has scheduled |
|---|---|
| December 2026 to early spring 2027 | Winter shutdown |
| Spring 2027 | Landscaping, sign installation, general cleanup, demobilization |
| Next construction season | New controller cabinets, final paving and markings, updated signal timing |
| July 2027 | Project completion |
Until December, the work continues around you. This week's schedule includes overnight curb work and daytime barrier installation under the I-89 overpass, with two-way traffic kept open on U.S. 2/7. Lane closures change from week to week, so the VTrans Exit 16 weekly updates are the best place to check before a trip at a busy hour.
Once the shutdown starts, Exit 16 will stay in this half-finished state through the snowy months, with temporary timing at Mountain View Drive, some dark pedestrian signals and the deliberate holds at the edges. VTrans says to expect an adjustment period while drivers get used to the pattern and while construction continues toward completion in summer 2027. The final version of Exit 16, with its own signal phases and a finished path from South Park Drive to Mountain View Drive, is scheduled for next July.
Roads, paths and bus routes shape daily life in a town, and Kace pays close attention to that kind of infrastructure when he looks at Colchester. If you're wondering how projects like Exit 16 affect the parts of town you use every day, or which ones are coming next, idENTITY real estate group is happy to talk it through. Get in Touch.
Stay up to date on the latest real estate trends.
We combine local expertise, strong communication, and thoughtful strategy to create an experience centered around your goals. At idENTITY real estate group, you’re never just another transaction — you’re part of the community we care deeply about.